Bulk Power Highlights

March 2001

Each document summarized in the Bulk Power Report may be found at: http://rimsweb1.ferc.fed.us/rims

 

NORTHEAST

Utility.com has terminated its membership in NEPOOL. ER01-1289.

NEPOOL has revised its Billing Policy. ER01-1155.

Model City Energy is building a generating facility in Niagara County, NY. ER01-1192.

EnviroPower is building a generator in Hazard KY. ER01-1280.

NYISO is modifying its ICAP market. ER01-1213.

PECO is selling capacity and energy to Commonwealth Energy to provide retail service. ER01-1215.

Allegheny and PJM have set out procedures for handling interconnection requests. ER01-1223, 1232.

Consumers Power is transferring its transmission assets to the International Transmission Company. ER01-1301.

Whiting Clean Energy has filed for marketer status. ER01-1300.

Dearborn Industrial Generation plans a new powerplant in Dearborn, MI. ER01-1303.

PJM has filed its OATT. ER01-1343.

SOUTHEAST

Doswell and Virginia Power have entered into a sales agreement.

Cleco and Acadia have entered an agreement for a Phase Shifting Transformer. ER01-1295.

SOUTHWEST

Enron Sandhill LP has filed for marketer status. ER01-1166.

PG&E is constructing a new 230 kV substation to connect Duke's generating plant to the CA grid. ER01-1230.

NORTHWEST

BPA and Puget Sound have entered storage arrangement for delivery and redelivery of power. ER01-934, 940, 1009.

RTO Filings

NORTHEAST

Joint petition to form New England Regional Transmission Organization. RT01-86.

SOUTHWEST

Submission of SDG&E regarding reforms needed by Cal ISO. RT01-82.

Submission of Cal ISO regarding progress toward becoming an RTO. ER01-85.

 

 

Summaries of all recent transmission and bulk power agreements are published monthly in the Wheeling & Transmission Monthly newsletter, which is available by subscription from:

Cogeneration Publications
Attn. Carol Ofiesh - Subscription Manager
P.O. Box 2303
Falls Church, VA 22042
Fax: (703) 641-9265
E-Mail: Centaur@erols.com

You may also contact us at centaur@erols.com for samples of
any of our publications or click on the icon below to subscribe online.

Click here to subscribe online